Hollywood Construction Company recognizes revenue over time according to percentage of completion for its long-term construction contracts. During 2018, Hollywood began work on a $3,000,000 fixed-fee construction contract, which was completed in 2021. The accounting records disclosed the following data at year-end:

Cumulative contract costs incurred Estimated costs to complete at end of year
2018 $200,000 $1800,000
2019 $1100,000 1100,000
2020 2,000,000 4,00,000

For the 2020 year, Hollywood should have recognized gross profit on this contract of :___________