A construction crew is completing about 40 yards of a new highway each day. At this rate, how long will it take them to complete a stretch of 1.6 miles? Round your answer to the nearest tenth if necessary

Respuesta :

Answer:

70 days

Step-by-step explanation:

that is the procedure above